Project Update - Cambridge House

January 29, 2021
View Post on LinkedIn

Project update: The first major concrete pour to Building 03 took place last Thursday. This was a 250m3 pour and was all completed in 8 hours. This will be one of 5 pours to the Basement level 4 raft, with a total pour size for the raft of over 1000m3.

Our Cambridge House project, Piccadilly, the Former Lord Palmerston residence, and subsequent Naval and Military “In & Out” Club, together with the surrounding buildings are being converted into a Luxury Hotel and Private Residences.  

Deconstruct (UK) Ltd £45m redevelopment package involves the deconstruction of the existing structures, retention of the Listed façades and staircase structure, with piled excavation of 4 levels of basements, and subsequent building reconstruction.